Work continues on the North Atherton Street Project. The contractor will be installing soil and seed along South Barkway and Wooded Way starting on September 27th.
Below is the update from Ameron Construction Company:
- This week we have completed the install of Phase 3 sidewalk.
- 9/25-26: Installation of the temporary push buttons on the Phase 3 side of the project
- 9/27-29: Complete topsoil installation and seeding on the Phase 3 side of the project. Once sidewalks are backed up we will open the phase 3 side and switch traffic control to begin work on Phase 1 Area
- 10/2-6: Complete Phase 1 drainage, excavation, and install curb
- 10/9-13: Paving and final cleanup of Phase 1 area of project
- 10/16-20: Demobilization until permanent signal poles are available